Power - Hydro turbine - 2,000 kW
Template assignment
Base case
The worked-out solution is the data file selected from within the RETScreen Project Database. The user automatically downloads the Project Database file while downloading the RETScreen software.
Template assignment
Base case
- Central grid connection
- 2 MW run-of-river hydro plant with 80% capacity factor
- Cost is $5,000/kW installed, no dam required
- Electricity can be sold to grid for $0.10/kWh
- Operating cost are $200,000 per year
- Project life is 35 years