Natural Resources Canada logo and Government of Canada logo
Symbole du gouvernement du Canada

Power - Wind turbine - 50,000 kW

Template assignment

Base case
  • Central grid connection
Proposed case
  • 50,000 kW wind farm
  • Capacity factor estimated at 30%
  • Costs $2,000/kW for complete installation
  • Electricity can be sold to grid for $0.10/kWh
  • Annual costs are $3,500,000
Solution

The worked-out solution is the data file selected from within the RETScreen Project Database. The user automatically downloads the Project Database file while downloading the RETScreen software.