Energy efficiency measures - Industrial - Process heat
Template assignment
Base case
The worked-out solution is the data file selected from within the RETScreen Project Database. The user automatically downloads the Project Database file while downloading the RETScreen software.
Template assignment
Base case
- Natural gas fired boiler operating at 70% seasonal efficiency provides steam to load of 2 million Btu/h
- Load operates 45 hours per week at 100% duty cycle
- Load and duty cycle reduced by 25%
- Operating hours reduced to 40 hours per week
- Cost of changes estimated at $100,000
The worked-out solution is the data file selected from within the RETScreen Project Database. The user automatically downloads the Project Database file while downloading the RETScreen software.