Energy efficiency measures – Residential – Apartment building – Performance analysis / China
Template assignment
The heating needs of an apartment building located in Shenyang, Liaoning, China, are met by a district heating system. Determine the energy savings achieved after the installation of water flow restrictors in the showers of each apartment. Also, determine the non-weather dependent energy consumption.
Teacher's notes
Follow these steps:
Start
Whole data set: 2008-2011
Reporting
The worked-out solution is the data file selected from within the RETScreen Project Database. The user automatically downloads the Project Database file while downloading the RETScreen software.
Template assignment
The heating needs of an apartment building located in Shenyang, Liaoning, China, are met by a district heating system. Determine the energy savings achieved after the installation of water flow restrictors in the showers of each apartment. Also, determine the non-weather dependent energy consumption.
Teacher's notes
Follow these steps:
Start
- ►Select climate data for Shenyang/Dongta
- Step 1 - Consumption: Import fuel consumption data (district heating energy consumption data in kWh units) by selecting the user-defined fuel in the fuel list (Template_EEM_Residential_Apartment_Performance_Analysis_China.csv)
Step 2 - Factor of influence: Download NASA weather data
Step 3 - Data processing:
- a. Calculate heating degree-days (the reference temperatures is estimated
at 18°C)
b. Merge heating degree-days into the district heating data table
Whole data set: 2008-2011
- Step 1 - Baseline: Establish the baseline based on the entire duration of the data set using the regression analysis
Step 2 - Target: Skip this step
Step 3 - Comparison: Generate a CUSUM graph
- Step 1 - Baseline: Establish the baseline based on the period prior to energy efficiency measure implementation using the regression analysis
Step 2 - Target: Set the target to 0 or skip this step
Step 3 - Comparison: Generate a CUSUM graph
- Step 1 - Baseline: Establish the baseline based on the actual district heating energy consumption (i.e. period after energy efficiency measure implementation) using the regression analysis
Step 2 - Target: Set the target to 0 or skip this step
Step 3 - Comparison:
- a. Generate a CUSUM graph
b. Generate a control chart to track energy performance on a continuous basis
Reporting
- Step 1 - Report: Create a report for managers
Step 2 - Edit: Insert an optional text page to describe the analysis
Step 3 - Output: Export the report in PDF (*pdf) format
The worked-out solution is the data file selected from within the RETScreen Project Database. The user automatically downloads the Project Database file while downloading the RETScreen software.